How Long Does It Take to Draw a Floor Plan

#i Guest_Ross_*

Posted 11 February 2017 - eleven:22 AM

How long in does information technology take to make a full set of buildable plans? For a business firm in the 2000 - 3500 sqft upper and lower. 4-vi bed 2-3 bath.
All possible information needed to build and complete project. Inner designs and selections also as outside site work to calibration. -Hours to consummate per project-

#2 randolph cohn

randolph cohn

  • Location marin canton - california

Posted 11 February 2017 - 12:41 PM

100 to 500 plus hours.

depends on

clients

complexity of site & blueprint

location of project -

building and planning departments

review boards

professional engineering science required ?


  • Allen McDonnell likes this

randy

v10 to futurity 2016+ ;)

#3 Kevin Rabenaldt

Kevin Rabenaldt

  • Location San Antonio

Posted 11 February 2017 - 12:50 PM

Interesting question.  But what is the reason for the question?  Thinking of what to charge for pattern, looking at means to decide if you like to practice this for a living, checking the price of design work?  If of class depends on many factors.


#4 Keith Almond

Keith Almond

  • Location Brockville, Ontario, Canada

Posted xi February 2017 - 01:57 PM

That's actually a question that doesn't have an respond. Some people put much more than time, try and cognition into a set of plans than others. I know of some people who say they can complete a set of building permit drawings in one day. Personally, I take by and large between 3 and five days from initial sketch to complete let drawings. Still, they don't include interior elevations, selections or site work.

I like to think that my drawings are amend and more complete than nearly that I see, and that the extra time spent tin can relieve the customers many dollars on site. I've seen some really good drawings that have had many hours spent on them, and as well seen some really poor drawings that oasis't.

Mostly, you go what yous pay for. If your prepared to pay someone to spend a calendar month on ane project, so you should get very detailed and consummate drawings.

Are you asking from the point of view of a customer, or a designer?


Keith

There are 10 types of people in this world ....... Those who understand binary, and those who don't.

Softplan user since version 5.5.2.5

www.homehardwarekingston.ca

#5 randolph cohn

randolph cohn

  • Location marin county - california

Posted 11 February 2017 - 03:39 PM

also observe out if the clients plan on hiring an interior designer,

mural designer/architect and any others to work with

you lot and clients on the projection.

these extra designers can add together a little or a lot of hours to

your time and exist a real pain in the _ss

but if

you work skillful together, it tin can mean a lot

of futurity work with their clients.

so endeavour "NOT" to burn whatsoever bridges


randy

v10 to future 2016+ ;)

#half dozen Jim Crook

Jim Cheat

  • Location Gravenhurst, Ontario, Canada

Posted 11 February 2017 - 04:08 PM

It as well depends on how fast your Designer is.   I could take twice as long as Keith to produce the aforementioned equal project output.   Does that mean I can

charge twice as much for the project in the marketplace ?  I don't think and so.  It probably means I won't make as much equally the Designer that is faster

than me.    I'k really not sure how many base their fees on a very specific analysis of hourly input vs an overall gut feel based on previous experience.

In my example I approach it more than from the gut experience army camp based on my knowliedge of other jobs I've done in the past.

Over fourth dimension you kind of get to know where you need to be.


#7 randolph cohn

randolph cohn

  • Location marin county - california

Posted 11 February 2017 - 09:xx PM

jim,

I now only do "flat fee" contracts

using my noesis and gut feeling

from many decades of designing.

when I first started in the pattern field,

I go on all hours worked on whatever particular project.

now information technology's really as you lot say,  'my GUT FEELING'


randy

v10 to future 2016+ ;)

#eight Steve and Carla Farnam

Posted 12 February 2017 - 09:fifteen AM

Tough question to answer given all the unknowns. Some of our plans have been completed within

3 weeks of showtime meeting while others 2+ years. Nosotros likewise 'frame' ( on Softplan ) every house we design

to verify all parts piece of work before sending out the finished plans which takes a few extra hours. Crude

Gauge 80 to 120 bodily piece of work hours per boilerplate 2500 square foot custom dwelling house.


#nine John Jones

John Jones

    Advanced Member

  • Administrators
  • 251 posts

Posted 12 February 2017 - x:47 AM

How long does information technology accept y'all to create a "... full set of buildable plans..."  now?


#10 Steve and Carla Farnam

Posted 12 Feb 2017 - 12:46 PM

What is included in your " full set up of buildable plans' ? Plans for permitted jurisdiction or

area where edifice permits not required?


  • Allen McDonnell likes this

#11 Steve Haarmann

Posted 12 February 2017 - 03:36 PM

You will get answers all over the ballpark!

My answer is very simple - in one case you have your standards set up yous volition be farr faster with Softplan than whatever you are using now.

I routinely create consummate (yet basic) program sets of 2,000 to ii,500 sq ft in 18 to 24 hours.

This is Not including what I call (and bill) every bit "design time".

Obviously y'all tin can spend far more than than that with highly detailed interior elevations and sections, framing plans, etc. etc.


  • Rick Kingsbury likes this

#12 Tom Rogers

Tom Rogers

  • Location Villa Rica, Georgia

Posted 13 February 2017 - 08:42 AM

I am besides in the eighteen-24 hour range after I accept put the edifice together (3D model).  Labeling and dimensioning are fairly quick just is does depend on the detailed aspect of what you lot are looking for and complexity (curved or angled walls, lots of special items that need noted).  I have guys who can finish a drawing in 10 hours while it might take me 24.  Same firm. Just the speed of knowing the program.  A good CAD tech is worth a decent price.  Much rather pay someone $xxx/hour for x hrs of drafting than ane at $15/hr for 24 hours.  That $60 savings I could get is not worth the money I lose in waiting an additional 14 hours


  • Mark Tidwell likes this

#13 Steve and Carla Farnam

Posted thirteen Feb 2017 - eleven:45 AM

The hours for a total set of finished plans I mentioned above includes all meeting time with the client,

development of the design from concept through final preliminary program approval which includes floor plans

exterior elevations ( 3D rendered ), afterwards the preliminary approval final labeling , dimensioning etc goes

adequately quickly with final number of hours to complete dependent upon edifice location and local requirements.


#fourteen Guest_Ross_*

Guest_Ross_*

  • Guests

Posted xiv Feb 2017 - 07:17 PM

Thank you for the input. I am drafting Plans from scribble sketches of modified existing drawings in some cases and others from a scratched thought.

I tin can generally get the basic

Elevations, upper, main and lower floor with floor layout and roof with an 3D outside Render in well-nigh 4-5 hours. These are non finals or ready for permit.

Then when approved will cease out the plan in particular with plot site info septic course drainage for permitting. That also depends but normally takes nearly 10 to 24 hours.

I don't know anyone else that knows Softplan to gauge my speed. Been using Softplan about 2 years now. I am being pressured to go much faster and I wanted to see what others are doing to compare of how I am doing.

In many cases it will take longer or less time depending on a number of obstacles. My deadlines are always

right now similar its on fire. I besides wanted to see if anyone had any tips on setting up blocks that I make on my ain for details. Most of the time they are on an every bit needed basis. I have gear up my system options up with all of my wall details for ease of employ. as well as the floor systems.

Ross


#xv Keith Almond

Keith Almond

  • Location Brockville, Ontario, Canada

Posted xiv February 2017 - 09:49 PM

The more than you lot do, the more you'll be expected to do. You tin but add then much item in so much time. The more detail, the slower the drawing. The faster the drawing, the less complete. Only you tin judge how much detail that you are going to provide.

I don't think that fourth dimension taken to draw with Softplan (or whatever other CAD system), varies greatly betwixt users. What does vary greatly is the level of detail that each user provides.


  • Mark Tidwell and Tom Rogers similar this

Keith

In that location are ten types of people in this world ....... Those who sympathise binary, and those who don't.

Softplan user since version five.5.2.5

world wide web.homehardwarekingston.ca

#sixteen randolph cohn

randolph cohn

  • Location marin county - california

Posted 15 Feb 2017 - 11:16 AM

tips :

what to accuse for pattern drawings

(this includes all hours spent on design & meetings with all concerned

 and upwardly to and including blueprint development)

I charge approximately 2/tertiary of the total time for what we'll call

the "Design" fourth dimension

and

1/tertiary the total time for the construction documents.

reason for charging the largest corporeality for the pattern is

that's what your clients have hired you for and yous

should get the biggest chunk when this is finished.

and if your clients want to become cheap on you and rent

someone to do the drafting, at least you get your fair share.

note: y'all might even charge a larger amount for

the blueprint stage.

btw,  you lot can spent a lot more fourth dimension on the design and meetings.

and if you accept your multi drawings or plan sets in lodge,

you can spend way less time on the con docs.


randy

v10 to future 2016+ ;)

#17 Guest_3 Putt_*

Guest_3 Putt_*

  • Guests

Posted 22 Feb 2017 - 03:23 PM

three Days boilerplate.. When I first started cartoon prints it was considering all the ones I was trying to build off of were incorrect. We would sit on the tailgate of the truck and wash the entire print... 5 inch interior walls, 4 inch interior walls, dimensions being pulled from the brick on the exterior walls. I've seen it all. You give a print to 5 good crews and you get 5 different houses. Keep information technology uncomplicated.  Some of the best prints are fatigued by the people who actually do the work. I similar to think I could build every firm I draw.


  • admin likes this

#18 Tom Rogers

Tom Rogers

  • Location Villa Rica, Georgia

Posted 22 February 2017 - 05:25 PM

The more you do, the more yous'll be expected to exercise. You can just add together so much detail in so much fourth dimension. The more than detail, the slower the drawing. The faster the drawing, the less complete. But you can judge how much detail that yous are going to provide.

100% hold Keith.  I tin do a "basic architect set" (elevations, floor programme, roof and electrical - no details or sections) in a mean solar day.  Only I am not happy with it.  Each drawing I want to add more.  That is why I at present toll myself that way with a la carte add ons.  Customer knows what they are getting.  If they want more they need to pay more


#nineteen Guest_3 Putt_*

Guest_3 Putt_*

  • Guests

Posted 04 March 2017 - 08:16 AM

In all honesty half the fluff nosotros put on these prints don't even get looked at. We double and triple characterization everything. Phone call it out on the xsection and so turn around and call it out on the elevations again. When out in the field virtually carpenters don't even look at our details...These guys are machines and we cant tell them much. Become the foundation correct and go your floorplan numbers right and get out of the way.  Some of these guys I swear accept auto pilot. Wrong info is worse than no info..


#20 randolph cohn

randolph cohn

  • Location marin county - california

Posted 04 March 2017 - 12:48 PM

tip:

as putt says,

label the aforementioned thing only "Once" on the plans.

where-ever you lot call up is the best place.

DON'T brand things difficult.

call up,  there are "builders sets" and "for bid" sets of drawings.

two very different animals with a large difference in amount of

time to consummate each ready.

somebody mentioned their dominate wanted them to "do information technology faster"

no thing how fast it was done.

there are some people who you can "NEVER" please.


randy

v10 to future 2016+ ;)

schachtcied1946.blogspot.com

Source: https://softplan.com/forum/index.php?/topic/2280-timeframe-of-full-plan-drawing/